Planning backwards from a fixed date: the acrylic lead time chain

Lead time is not one number. It is a chain of seven steps, and the date fails at whichever link was never scheduled.

~1,600 words · 8 min read · Updated 2026-11-10

When a customer asks how long an order takes, the honest answer is a chain rather than a figure. Sampling is 3 to 7 business days and production is 7 to 15, but those two numbers only describe the middle of the process. The steps on either side are where dates are lost.

The chain

The seven steps from enquiry to installed part
StepTypical durationWho controls it
1. Enquiry to quotation1–3 business daysUs
2. Drawing check and clarification1–3 business daysBoth
3. Drawing approval1 day to weeksCustomer
4. Sampling / first article3–7 business daysUs
5. Sample approval1 day to weeksCustomer
6. Production7–15 business daysUs
7. Packing, freight, customs, site delivery2 days to 5 weeksFreight, customs, site

Steps 3 and 5 are the customer steps and they are where most schedules actually slip. Step 7 is the longest and least predictable, and it is the one most often left out of a plan.

The two numbers we quote are steps 4 and 6

It is worth being explicit about what they mean. Sampling is 3 to 7 business days for a first article, counted from an approved drawing. Production is 7 to 15 business days for a batch, counted from sample approval or from the drawing approval if no sample is required. Business days exclude weekends and public holidays.

  • 3 to 7 days covers a single part with standard finishing. A part with hand polishing, bonding and printing sits at the top of the range.
  • 7 to 15 days covers a normal batch. A mixed-material set, a bonded assembly or an anodised frame supplied by us sits at the top.
  • Neither number includes freight, customs or site access.
  • Neither number starts until the drawing is approved in writing.

Working backwards from a date

Take the date the part has to be on site, not the date it has to be ordered, and subtract:

  1. Site delivery and installation buffer: 3 to 5 days for domestic, 2 to 5 weeks for sea freight.
  2. Freight transit and customs: the actual quoted transit, plus a week for a first shipment on a new route.
  3. Packing: 2 to 4 days for crated parts.
  4. Production: 7 to 15 business days.
  5. Sample approval: assume 3 to 5 days even if the customer is fast.
  6. Sampling: 3 to 7 business days.
  7. Drawing approval: assume 3 to 5 days; add a round of revision if the part is new.
  8. Enquiry and quotation: 3 days.

For an international exhibition with a fixed opening, that chain typically comes out at four to five weeks before build-up. Anything shorter is possible for simple parts but should not be assumed for a bonded vitrine with lighting.

Where schedules actually slip

The five real causes of a late acrylic order
CauseTypical delayHow to avoid it
Drawing not approvedDays to weeksApprove against a marked-up drawing within 48 hours; nominate one approver
Sample revisions1 to 2 weeks per roundSend the frame dimensions and a reference photo with the first order
Sheet grade not in stock5 to 10 daysSpecify the grade early; ask us to confirm stock at quotation
Adding a finish after quoting2 to 5 daysConfirm the finishing scope before release
Freight and customs3 days to 3 weeksBook the forwarder at order, not at completion

Where to put the slack

Slack in the wrong place is wasted money and slack in the right place is insurance. The right place is freight and site delivery, not production. Compressing production to buy freight time means overtime rates and a higher defect risk; holding two weeks of freight buffer costs nothing but a slightly earlier order date.

  • Build the buffer into freight and installation, not into the factory schedule.
  • Order the sample early even if production is months away; the sample is the design review.
  • For a rollout, send the first store as a pilot and let the remaining stores follow on a call-off.
  • For a show, ship to the venue rather than to the office if the venue will accept freight in advance.

What we will and will not promise

We will give a dated production commitment at order, tell you the day we know if something is slipping, and split a shipment if part of the order is ready and the date is at risk. We will not promise a date that depends on someone else approving a drawing on a day they have not committed to.

Questions this article answers

A single flat part in stock material can sometimes be cut in 3 to 5 business days. Polished, bonded or printed parts cannot be compressed much below the sampling range, because the finishing is hand work.

Sometimes, on a batch where the constraint is machine time. It does not help when the constraint is material, drying or a customer approval, and we will say which constraint is real.

Air express is typically 5 to 10 days door to door; sea freight is 3 to 6 weeks depending on the route. Both exclude customs clearance, which varies by destination.

Yes, on a call-off agreement with a defined storage period. Holding stock decouples the customer schedule from our lead time, which is the usual arrangement for a rolling build plan.

We tell you the day we know, not the day the order ships, and we offer what is achievable: a partial shipment, an air upgrade at shared cost, or a re-sequenced batch. A missed date is a conversation, not a surprise.

Give us the on-site date, not the order date

We will work back through the chain and tell you where the schedule is actually tight.